Construction of Jokeri Light Rail 75% complete – rail construction progressing ahead of schedule

The construction of Jokeri Light Rail has proceeded ahead of schedule. The rapid pace of construction now means that the light rail line can start operating about five months earlier than planned, i.e. early 2024. The construction in the Espoo section will mostly be finished in 2021.
Raide-Jokeri
Image: Jokeri Light Rail

Of the construction of Jokeri Light Rail, 75 per cent is now completed. We reached the milestone of three quarters at the end of October 2021. Rail construction has progressed ahead of schedule, and 21 kilometres of the 25-kilometre rails are now finished. 

The original target was having completed 20 kilometres of the rails by the end of 2021. Expectations were exceeded thanks to successful resourcing, coordination of schedules, and developing working methods. Most of the construction in the Espoo section will be completed in 2021, while the construction of the Keilaniemi terminus will continue in 2022. The installation of the overhead cables and finishing touches both on the line and the power supply stations will continue in Espoo in 2022.

In 2023, we will add the finishing touches to the Jokeri Light Rail worksites. We will also run commissioning tests and test traffic. The operation on the light rail should start in January 2024.

Text by Jokeri Light Rail

More information

Konemiehentie.jpg

HSY's contstruction site remains in place on Konemiehentie

Exception routes in the Konemiehentie - Sähkömiehentie area will continue until the end of November 2021. Exceptional route arrangements will also remain in place until the site is completed.

Kartta liikennejärjestelyistä2.jpg

Konemiehentie between Puumiehenkuja - Sähkömiehentie is closed until the end of November 2021.

  • Updated:
  • Published:
Share
URL copied!

Read more news

Four people sitting on chairs with a large screen behind them showing Aalto University's Marsio event information.
University Published:

Aalto University’s open-to all events in autumn 2025 will take you on a journey into research and art – discover also the new Marsio building

The events are produced in collaboration between Aalto University and the City of Espoo and they will take you from the flood of information to deeper insights.
Aalto Creatives Demo Day photo
Campus, Cooperation Published:

Startup Spotlight: Aalto Creatives Demo Day Celebrates New Innovations

Aalto Creatives pre-incubator programme hosted a Demo Day event at Marsio’s Living Room Stage in the end of May. The event featured eight pre-incubator participants showcasing their early-stage companies and a panel discussion about investing in the creative industries.
Vaahtera kampuksella
Campus Published:

Nature at the core of Aalto's campus plan

The trees in the Otaniemi manor area were significant to Alvar Aalto.
Kuvassa näkyy viisi opiskelijaa aurinkolasit päässä. Opiskelijat seisovat kehässä, ja kuva on otettu sen keskeltä alhaalta päin.
Studies Published:

Aalto University admitted 2053 new students to BSc programmes taught in Finnish or in Swedish

Aalto University has admitted 2053 new students to its bachelor's programs conducted in Finnish or Swedish. New students were also selected via the open university pathway and transfer application.