Otaniemi already has 1,800 metres of track

Next, the construction of the track in Otaniemi will continue on Vaisalantie and Ainonaukio and Korkeakoulunaukio.
The rails will be transported to the construction sites in segments that are approximately 18 metres in length. The transportation and laying of the rails requires a large amount of space, due to which the construction may cause temporary traffic interruptions. To ensure smooth traffic flow and safety, construction may also be carried out at night. Local residents will be informed in advance of construction taking place at night.
After the laying of the rails, work on the streets will proceed to other tasks, including the construction of the rail line’s surface structures and other street segments.
The Otaniementie end of Miestentie was closed to motor traffic in early September. The construction work at the intersection of Miestentie and Otaniementie will last for approximately eight months. Pedestrian and bicycle access will remain around Miestentie throughout the construction project, but it will be rerouted according to different stages of construction. Signs will be posted to instruct pedestrians and cyclists on Otaniementie.
Work on water services, district heating welding and operator piping will be conducted on Otaniementie. The electric railway foundation work on Korkeakoulunaukio and Ainonaukio has been completed. Compensation pipes will be put in place in Ainonaukio. Pedestrian and bicycle access will remain around Korkeakoulunaukion ja Ainonaukion throughout the construction project, but it will be rerouted according to different stages of construction
Finishing work will be conducted at the intersection of Konemiehentie and Tietotie. Track work and greenery planting will be conducted on Maarinrannantie.
More information
Text: Raide-Jokeri
Read more news

Research result: Customer satisfaction with Aalto University campus premises remains high
ACRE assesses the satisfaction of its facility tenants through a customer satisfaction survey. Read about the results of the latest survey.
Spring term open science highlight: Aalto Open Science Award Ceremony
We gathered at A Grid to celebrate the awardees of the Aalto Open Science Award 2024 and discuss open science topics with the Aalto community.
Aaltonians satisfied with the Kide building
Kide has been seen as a successful building.